Remodelling of two Year 2 Classrooms
The original configuration was designed with two small classrooms (35m2) sharing a Resource area (23m2) which was severely undersized by current standards which recommend classrooms of 56-63m2 floor area.
Our design solution involved remodelling the area to provide two self contained classrooms 58m2 and 64m2 whilst improving the previously lacking acoustic separation, thermal insulation, solar gains, ventilation, heating, lighting and aesthetics by fully refurbishing the area.
The project was delivered in a very tight timescale and the school were delighted with the end product.
We could not be more delighted with the work completed at St. Ann’s, it really is outstanding. The management of the project was fantastic. WAND ensured it was finished on time, within budget and with minimal mess and disruption to our children and staff
Neil Shaw-Binns (Site Manager)